Project Name: Aaron Court, Luton
Client: Warden Housing Association Limited
Value: £51,000.00
Duration: 12 weeks
Services Provided: Design, Contract Administration and Planning Supervisor Services.
Description: Replacement of heating and hot water installations within 22 flats together with the removal of existing asbestos materials. The works were carried out whilst the tenants were in full occupation and completion was achieved within the programmed dates.